The College of Medicine Learning Center Project continues to make advancements with an ambitious agenda.  Once again we would like to provide specific updates about the movement of the project.

  • The Learning Center Project continues on an accelerated schedule to meet our August deadline for the space to be functioning for instruction. 

  • Demolition on the 2nd floor is complete and the space is now being prepared for fireproofing and infrastructure upgrades.

  • The original window openings located in the 2nd floor auditorium have been fully revealed, which will add a considerable amount of natural light into the restored space.

  • The 3rd floor fireproofing was completed last week and the new service line supplies for water, power, and HVAC are being hung from the ceiling.

  • On the 4th floor, the walls for the new Chicago Student Medical Student Council Office has been framed.

  • The 4th Floor power supply panels have been installed and the contractors are now routing the service lines to the individual classrooms.